Landfill Gas Generation Project in Laogang, Shanghai

Completion time:July 2013
Business model:EPC general contracting
Project overview:
Laogang Phase IV project was located near the beach of East China Sea at the east side of Laogang Town, Nanhui District, Shanghai, covering an area of 3.36 square kilometers, about 60 kilometers from the urban center. Project design and production capacity was to process 4,900 tons of municipal domestic waste per day. The phase IV project of Shanghai Laogang domestic waste landfill site entered trial operation on February 21, 2005. The principal part of the project was officially put into operation on December 12. The total investment of the project was RMB 510 million.

Process routes:
7×1409kW landfill gas internal combustion generator unit+5100 m3/h biogas pretreatment device
主要技術經濟指標:
年發電量:1805MWh
年產熱量:3028MWh
主要設備國產化率:25%
年利用小時數:3760h
總能利用率:83%
年節約標準煤:465t
年減排二氧化碳:1232t